Home >  Policies and Laws

Metrology Certification for Product Inspection Agencies

Update : 2015-12-08

(2) Acceptance

A decision on acceptance or rejection of the application shall be made within 5 days from the date of receiving the application and a written notice shall be issued.
(3) Review

The Bureau shall entrust an intermediary agency to arrange on-site review of the applicant within 2 months after accepting the application.

4) Ratification and Issuing Certificate:
The Bureau shall finish examination of the application and review materials within 20 working days. Where the requirements for issuing the certificate are met, the Bureau shall issue the certificate to the applicant. Where the requirements are not met, a written notice shall be given to the applicant.

6 Time Limit
An administrative decision granting accreditation shall be made within 20 working days from the date of acceptance (excluding time for review). The Certificate of Metrology Certification shall be issued within 10 working days from the date of an administrative decision granting authorization is made.

7 Fee
According to the notice on printing and distributing of metrology charge standards of General Administration of Quality Supervision, Inspection and Quarantine, State Planning Commission and Ministry of finance (Issuance No 323 (1991) of AQSIQ), the fee for metrology certification is 1200 RMB per application and the fee of Certificate [original unfinished]

 